"CRSA Aston purple team have completed a coupled lift using 6 TRMS - AN INDUSTRY FIRST - as well as using 8 way det-comm radios at Orton Station. The team completed 500 yards CAT12 all with no accidents or incidents.

Using 6 TRMS meant the team could take out and re install 110 yards of panels. This job was one of the first to be fully 4D planned as it was deemed undeliverable at the time of development, which with the help of the everybody, proved this wasn't the case and the team also slid in 233 yards of stressing at the end creating no CRT issues.

The Aston team have been really busy lately. Week 45 the team completed Arley tunnel East - 147 yards Cat 14 fully stressed and then West doing 470 yards Cat 2. Week 46 was Church lane - 1000 yards Cat 2 and this weekend at Orton."